Skip to main content

Advertisement

Table 4 Analysis results with an attacker positioned on a Smart Meter

From: Load balancing of renewable energy: a cyber security analysis

Variants 1st & 2nd RTUs DER RTU SCADA servers
Model variant A (no DMZ / less secure) 84 days 83 days 78 days
Model variant B (no DMZ / more secure) 200 days 185 days 172 days
Model variant C (DMZ / less secure) 169 days 165 days 148 days
Model variant D (DMZ / more secure) 200 days (37%) 200 days (50%) 200 days (45%)